Product Details:
Payment & Shipping Terms:
|
Product Name:: | Fresh Keeping Cold Storage Of Fruits And Vegetables With Package / PUR Sandwich Panel Assembling | Rerigerant: | R22,R404a,R507a |
---|---|---|---|
Application: | Fresh Keeping And Storage | Size: | 1000 To 2000 Tons |
Room Temperature: | -5C~+10C | Structure: | Steel Structure And Insulation PUR Panel Assembling |
Warranty: | 1Year | Compressor Brand: | Bitzer (Beijing Factory) |
Insulation Panel Type: | Colored Steel,stainless Steel,riffled Steel Board | Panel Thickness: | 100/120mm |
High Light: | agriculture cold storage,cold storage for tomato |
Fresh Keeping Cold Storage Of Fruits And Vegetables With Package / PUR Sandwich Panel Assembling
Quick details:
Compatitive Advantages
Fresh keeping Cold storage Application
Vegetables Distribution center,Farm and agricultural products market , Export center,Fruits processing factory etc
Steps of tailored cold storage
Step | Contents | Details |
1 | Client describe the requests and using methods | 1. Client provides some basic requirements; |
2. Client provides relative information: | ||
1) construction address, environment, weather, geology conditions, electricity supply; | ||
2) storage purpose and functions; | ||
Other design requirements | ||
2 | We offer sketch design and pric | 1. Communication on details, discussion and modification until reach an agreement; |
2. sketch design; | ||
3. price offer on all systems | ||
3 | Contract and formal design | 1. Sigh the former design contract (if any); |
2. Site survey and measurement (if necessary); | ||
3. Formal design and delivery; | ||
4. Details of solution and price. | ||
5. Client prepare the construction site and foundation. | ||
4 | Equipment and material export | 1. Sign the contract of equipment and materials; |
2. production and export preparation | ||
3. Client prepare the on-site electricity and water | ||
5 | Installation | 1. working procedure confirm and team organization; |
2. Construction teams go to install. | ||
6 | Check and acceptance | 1. Our technicians trial run the cold storage on-site; |
2. Client check and make acceptance. | ||
7 | Operation instruction and warranty | 1. training clients’ cold storage operators; |
2. provide technical support within the lifetime of cold storage. |
It dosen't include any part related to the civil work, e.g.
1. Foundation construction, the enforced concrete layer of floor(surface),
2. The water and electricity supply or distribution(need clients connect power to the machine room)
3. local government inspection fee
4. Fire fighting system
Main Factors affect the price
1. Machine's components quality level
2. Insulation panel quality level
3. Design
Cold room photos